Project Celestine began when our client came to us with a typical Toronto bungalow. They wanted their classic home to have significantly more living space provided by their three bedrooms, one bathroom, and a tight kitchen. Their aim was to build a full second-storey addition in Toronto with three extra bedrooms, walk-in closets, and two bathrooms. The project also included reconfiguring the main floor to create a more open layout, adding another bedroom, a powder room, and a three-piece bathroom.
We also built them a brand-new garage from the ground up and replaced the original brick exterior with a contemporary stucco finish. By the end of the project, their modest Toronto bungalow had undergone a major renovation, becoming a spacious two-storey family home of approximately 2,500 square feet.
Planning the full home addition in Toronto
Project Celestine began with our complete design-build process.
Our engineer first assessed the existing structure and prepared the initial drawings. The plans needed to account for the new second storey, the removal of the existing roof, the staircase opening, the garage foundation, and the connection between the original bungalow and the new construction.
There was a detailed back-and-forth process with the clients as we refined the layout, reviewed the finishes, and narrowed down the project pricing. Once the drawings were developed, our designer began working on the interior renderings, finish selections, and project schedules. The new interior design provided a modern feel, with bright neutral finishes, light hardwood flooring, white cabinetry, and black accents moving into the second storey with a fresh staircase connecting the two floors.
A project of this nature, involving HVAC, plumbing, electrical, and construction professionals, relies heavily on effective coordination. After the plans and pricing were approved, we prepared and submitted all necessary permit applications, and we scheduled our trades and deliveries to align with each stage of construction.
At this stage, the house looked less like a renovation and more like a blank canvas, as we had demolished and stripped it down to its frame to transform it into a brand-new home.
On the main floor, we removed walls to create an open layout designed for entertaining and opened the space for the new staircase, connecting the original main floor to the new level above. This step was essential because trying to build around systems and walls that no longer supported the new design would have constrained the project and could have caused issues later on. With the interior stripped down, we could effectively frame the new rooms, reroute the mechanical systems, and construct the home in accordance with our new plans for the full home renovation.
Removing the roof and framing the second storey addition
Removing the roof of a home is a very difficult task, but it was also one of the most schedule-sensitive aspects of this whole project.
Before starting this phase, it was essential that we coordinate all aspects and stakeholders of the operation. Once the roof is removed, the house becomes vulnerable, so we had to move quickly and stay coordinated before it snowed. It’s crucial to prevent water from entering the structure, and materials absolutely cannot be delayed while the building is open.
We removed the existing roof and framed the new second-storey walls. The roof trusses were then delivered to the property, where a crane helped lift and position them. The following day, the shingles were installed. The windows were also ready, so we could seal the structure as quickly as possible. This was one of the most important stages of this project.
Working through Toronto’s winter weather
Thanks to careful preparation and our coordinated team, we were able to carry on with Project Celestine throughout the winter.
We installed a large protective tarp around the work area, allowing our crews to continue working in a comfortable environment while keeping the home completely protected from the elements. Propane heating was used inside the enclosure to maintain more suitable working conditions for the crews and construction materials.
This approach added to the project’s cost, but it also allowed construction to continue rather than pause for the season. It helped us maintain the six-month construction timeline while keeping the existing home protected from the elements during this major home renovation in Toronto.
Once we opened the walls, we discovered that the original home had little to no effective wall insulation in certain areas.
By improving the wall assembly, we brought the older portion of the house closer to the comfort and energy performance expected from the new addition. Insulation performance is measured by R-value, which indicates how well a material resists heat flow. In simple terms, a higher R-value typically means greater resistance to heat loss. This also reduced the risk of having a newly insulated second story sitting above a main floor that remained cold and uncomfortable.
After the insulation work passed inspection, we boarded the new walls and moved on to drywall finishing. We applied multiple coats of joint compound to prepare the interior for painting and final finishes.
Replacing the Brick Exterior With Stucco
In order to establish the new aesthetic for our client’s home transformation, we felt it necessary to replace the bungalow’s traditional brickwork with a more contemporary stucco finish. The new finish allowed the original structure to blend with the second-storey and garage additions, creating a cohesive design.
We believed that the stucco application was the ideal finish to enhance our client’s desired contemporary aesthetic. The interior features bright neutral tones complemented by black accents, and the stucco’s neutral surface serves as a perfect introduction to the newly designed space. With subtle details like the parallel exterior lines, the stucco finish creates an impressive first impression for visitors and passersby.
Building the New Garage Addition in Toronto
Since the garage was a completely new structure, our work began underground. We excavated the area, formed and poured the concrete footings, and constructed the new foundation walls. To strengthen the connection between the new addition and the existing house, we drilled into the original foundation and epoxied steel reinforcing-bar dowels in place.
With the construction of an entirely new structure, attention to these processes is absolutely essential. The new construction must integrate properly with the existing structure rather than function as a separate entity. This structural connection was an essential part of the garage addition and overall home addition.
A complete Toronto design-Build transformation
Project Celestine exemplifies what can be accomplished when the planning, engineering, design, permits, construction, and finishing phases are managed effectively by an experienced contractor skilled in complex home renovations.
In just 6 months, we:
As a result, the finished 2,500-square-foot home provides our client with the necessary bedrooms, bathrooms, storage, and open living space without having to sell their existing property.
Are you considering a second-storey addition or a complete home renovation in Toronto?
Projects of this scale require engineering, permit coordination, structural construction, weather planning, skilled trades, and detailed project management. Contact SLG Contracting to discuss your property, goals, expected budget, and the steps involved in planning your Toronto home addition.